Attachie

A condensate-rich, natural gas play primed for large-scale development. Attachie is the leading development opportunity within our portfolio.

Quick facts

Facility Capacity
40,000 boe/day
60% crude oil and liquids
40% natural gas
2024 Objectives
Complete construction and commission Attachie Phase I in Q4 2024.
PDP Reserves1
90 MMboe

116 undeveloped locations booked representing 7% of internal inventory estimate

(1) Reserves as of December 31, 2023.

Phase I overview

In Q1 2023, ARC sanctioned the first phase of development of this high-quality asset. Attachie Phase I was successfully commissioned in Q3 2024 with full productive capacity expected by Q1 2025.

Phase 1 includes:

Oil_Barrel

40,000 

boe/day

facility capacity

Natural-gas

90 
MMcf/day

natural gas processing capacity 

25,000 
bbl/day

liquids-handling capacity 

Electrification

Electrified 

with renewable hydroelectricity to support low-emissions profile

Protect_Water

water recycling

infrastructure to reduce fresh water use 

Project schedule and progress

The project was completed on-time and on-budget in Q3 2024. Phase I was successfully commissioned in late October 2024 and production is increasing as planned towards productive capacity of 40,000 boe per day by 2025.

***All dates are anticipated based on the current project schedule.***

Project milestones

Q3 2024 Update

Attachie Phase I is now complete:

  • Construction was completed in Q3 2024 and the project was successfully commissioned in late October 2024.
  • Drilling operations for all 40 start-up wells have concluded and completions operations for the final start-up pad will commence in mid-November 2024.

September 2024 Update

Phase I of Attachie remains on track, with initial commissioning volumes anticipated in the fourth quarter of 2024. Plant construction is greater than 90 per cent complete and drilling and completion operations are progressing on schedule. ARC has drilled 37 of the initial 40 start-up wells, while 28 wells have been fracture stimulated.

Q2 2024 Update

Attachie Phase I is approximately 75 per cent complete:

  • ARC has drilled 30 of the approximately 40 wells required to fill the 40,000 boe per day facility capacity, and stimulated 20 wells.
  • Plant construction is approximately 75 per cent complete.
  • The transmission line, natural gas sales line, and water ponds are all complete.
  • The liquids and gathering pipelines are on schedule and nearing completion.
Selection for First-of-its-Kind Landscape Planning Pilot

In July 2024, the Government of B.C. and Halfway River First Nation announced an agreement which includes a Landscape Planning Pilot for an area that encompasses ARC’s Attachie development. As a result, Attachie is no longer limited by the disturbance cap for petroleum and natural gas development outlined in the Blueberry River First Nations Implementation Agreement.

 

Q1 2024 Update

Drilling and completion activity is progressing as planned. To date, ARC has drilled 22 of the approximately 40 wells required to fill the 40,000 boe per day plant capacity. The first Attachie Phase I pad was also completed in the first quarter. Other key milestones include completion of a pipeline bridge, plant construction is approximately 60 per cent complete, and all major equipment is on-site.

Q4 2023 Update

As of February 2024, Phase I is approximately 50 per cent complete. Drilling and completions activities have commenced, construction of the Phase I facility and related infrastructure is approximately 30 per cent complete, and installation of the gathering pipelines is approximately 40 per cent complete.

Q3 2023 Update

As of Q3 2023, construction of our Attachie Phase 1 facility is approximately 20 per cent complete. Key milestones achieved include: the natural gas sales line is installed, 75 per cent of facility pilings installed, water recycling ponds installed and compressor buildings installed.

Related

December 15, 2022

ARC achieves certification on 100 per cent of its production

/ News
Flood
December 22, 2021

Supporting B.C. flood relief

We value your privacy

We use cookies to enhance your browsing experience, serve personalized ads or content, and analyze our traffic. By clicking “Accept & Close”, you consent to our use of cookies policy